Bond-Construction Schedule

Phase I (LW St. John, North and South Annex, Grand Valley Middle School)

Phase II (Bea Underwood Elementary, Grand Valley High School)

Phase III (Center for Family Learning, Transportation and Maintenance Building)

 

Phase I Design  (February 2015 – May 2015)

Phase II Design (March2015 – August 2015)

Phase III Design (April 2015 – August 2015)

 

Phase I Construction

LW St. John (June 2015 – November2015)

North and South Annex (June 2015– August2015)

Grand Valley Middle School (June 2015– August 2015)

 

Phase II Construction

Bea Underwood Elementary (December 2015 – August 2016)

Grand Valley High School (November 2015 – August 2016)

 

Phase III Construction

Center For Family Learning (May 2016 – August 2016)

Transportation and Maintenance (December 2015 – May 2016)